Terrace Lane, Meadowlark Lane & Michael Lane
Road Reconstruction
Monday, November 22, 2010
Wednesday, November 10, 2010
The contractor is substantially complete with the work with the exception of manhole adjustments, pavement markings and remaining landscaping on Meadowlark and Terrace.
The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.
The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.
Friday, November 5, 2010
The contractor is substantially complete with the work with the exception of manhole adjustments, pavement markings and remaining landscaping on Meadowlark and Terrace.
The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.
The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.
Monday, November 1, 2010
Friday, October 22, 2010
The contractor has paved the final lift of hot-mix asphalt (surface course) this week on Meadowlark and Terrace.
The contractor has completed work on curb and gutter, driveway and sidewalk replacement this week on Michael. The contractor is scheduled to grind the existing asphalt pavement late this week and prepare for hot-mix asphalt paving into next week on Michael.
The contractor has completed work on curb and gutter, driveway and sidewalk replacement this week on Michael. The contractor is scheduled to grind the existing asphalt pavement late this week and prepare for hot-mix asphalt paving into next week on Michael.