Monday, December 6, 2010

Work is substantially complete with the exception of punch list work.

Tuesday, November 30, 2010

Work is substantially complete with the exception of punch list work.

Monday, November 22, 2010

The contractor is substantially completed with the work with the exception of remaining landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work.

Wednesday, November 10, 2010

The contractor is substantially complete with the work with the exception of manhole adjustments, pavement markings and remaining landscaping on Meadowlark and Terrace.

The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.

Friday, November 5, 2010

The contractor is substantially complete with the work with the exception of manhole adjustments, pavement markings and remaining landscaping on Meadowlark and Terrace.

The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.

Monday, November 1, 2010

The contractor is substantially complete with the work with the exception of landscaping on Meadowlark and Terrace.

The contractor has completed the hot-mix asphalt (surface) paving on Michael today (Monday, November 1).

Friday, October 22, 2010

The contractor has paved the final lift of hot-mix asphalt (surface course) this week on Meadowlark and Terrace.

The contractor has completed work on curb and gutter, driveway and sidewalk replacement this week on Michael. The contractor is scheduled to grind the existing asphalt pavement late this week and prepare for hot-mix asphalt paving into next week on Michael.

Friday, October 15, 2010

The contractor is scheduled to pave the final lift of hot-mix asphalt (surface course) next week on Meadowlark and Terrace.

Utility (water main) work has been completed on Michael Lane. The contractor is scheduled to work on curb and gutter, driveway and sidewalk replacement next week on Michael. Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter cures in front of their driveways. The contractor will notify residents that need to have their vehicles moved out of their driveways prior to concrete work.

Friday, October 8, 2010

The contractor will continue with utility structure adjustments on Meadowlark and Terrace into next week. The contractor is scheduled to pave the final lift (hot-mix asphalt surface course) on Meadowlark and Terrace in mid-October.

Utility (water main) work will be completed on Michael Lane this week. The contractor is scheduled to proceed with curb and gutter replacement and asphalt grinding later this month.

Friday, October 1, 2010

The contractor will continue with utility structure adjustments on Meadowlark and Terrace into next. The contractor is scheduled to pave the final lift (hot-mix asphalt surface course) on Meadowlark and Terrace in mid-October.

The contractor is scheduled to continue installing water services on Michael Lane into next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.

Friday, September 24, 2010

The contractor paved the first (of two) lift of asphalt on the northern section of Terrace this week. Next week the contractor is scheduled to complete utility structure adjustments on Meadowlark and Terrace.

The water main testing and chlorination has been completed and passed on Michael.
The contractor is scheduled to continue installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.

Friday, September 17, 2010

All concrete work on Meadowlark and Terrace has been completed. The contractor is scheduled to start preparation of the aggregate base course on Terrace late this week, continuing into next week. The contractor is also scheduled to install the hot-mix asphalt binder course next week (weather permitting).

The water main on Michael has been installed and is being tested / chlorinated.
The contractor is scheduled to start installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.

Friday, September 10, 2010

All concrete work on Meadowlark and Terrace has been completed. The contractor will be finishing the asphalt surface grinding this week on Meadowlark and Terrace.

The water main on Michael has been installed and is being tested / chlorinated.

Thursday, September 2, 2010

All concrete work on Meadowlark and Terrace has been completed. The contractor will be in by the end of this week to do some of the asphalt driveways.

The water main on Michael should be completed within the next few working days.

Friday, August 27, 2010

All the underground work is complete on Terrace and Meadowlark! Replacement of curb and gutter is underway and should be completed sometime next week. Upon completion of curb and gutter installation next week, the contractor will begin grinding the surface of the roadway off for resurfacing.

Watermain installation has begun on Michael Lane and will continue for the next several weeks.

Friday, August 20, 2010

The utility services are almost complete on Meadowlark and Terrace. Then there are just a few things left to do before curb & gutter work can begin, including removing existing fire hydrants. Curb and gutter removal and replacement should take place sometime next week.

On Michael Lane, the contractor is going to prepare the trench for water main installation. This is going to involve grinding the road surface exactly where the water main is going to be placed. This way, the rest of the road pavement will remain in place until the water main is installed. This grinding may take place today. The contractor plans to begin the water main installation early next week.

Friday, August 13, 2010

The utility services are almost complete on Meadowlark and Terrace. Work on Michael should be starting soon!

Saturday, August 7, 2010

Michael Lane

Work on Michel Lane should begin within two weeks.

Meadowlark/Terrace

The contractor is done with utility services on Meadowlark and is continuing with the services on Terrace.

Friday, July 30, 2010

The contractor is continuing on the utility services.

Friday, July 23, 2010

STRIKE HAS BEEN RESOLVED, CONSTRUCTION RESUMES!

The strike was resolved this week and new contracts between the unions and contractors have been signed and are in effect. The contractor resumed work this week!

The contractor began working on utility services this week. Every house is receiving a new 1.5” copper water service. A reminder: when replacing the water service, water to the house will be shut off for approximately 2 hours. The contractor will notify each house the day of the shut off. Sanitary and storm main and services spot repairs are also being completed at this time.

Tuesday, July 13, 2010

Strike Continues

As of this morning, the strike continues. The Unions and the Contracting Companies are still in negotiations and have not yet reached an agreement. It is our understanding that the next scheduled meeting is set for Monday, July 19.

We continue to ask for your patience and understanding during this time. We are continuing to monitor each construction site so that they remain safe to the general public.

As stated below, please do not hesitate to contact the Village Project Manager or the Capital Projects Department at (847) 998-9500.

Thursday, July 1, 2010

STRIKE NOTICE

Dear Resident:

Thank you for your ongoing patience during the Village construction project adjacent to your home. At this time, the Village has been notified that Chicagoland Construction Labor Unions are going on strike. The conflict is between the Contracting Companies and the Unions, not involving the Village.

Work has therefore been temporarily shut down on your street. We are insuring that all construction sites are safe to the general public and will continue to actively monitor each site.

If any issues arise, or if you should have any questions, please contact the Village Project Manager or the Capital Projects Department at (847) 998-9500.

As of today, we do not have any information on how long this strike could last. We will inform you when this issue is resolved and work will resume.

Thank you again for your patience while this matter is resolved.
The water main on Terrace passed the pressure test, so the next step will be to chlorinate it and then once that passes, water services can begin.

Friday, June 25, 2010

Water main line has been completed on Meadowlark and Terrace. The water main was pressure tested and chlorinated. We are awaiting the results of the chlorination, and upon approval, the contractor will begin water services. See post from last week for explanation of a water service installation.

Friday, June 18, 2010

Water main line should be completed on Meadowlark and Terrace in the next week. Once the main line is installed, it needs to be pressure tested and chlorinated. It’s actually quite a simple test, in that the main is filled with water and pressurized to 150 pounds per square inch (psi). To pass the pressure test, pressure must be held at 150 psi for 2 hours. Once the pressure test passes, the water main gets chlorinated, to disinfect the pipe. Once the chlorination tests pass, the contractor can begin replacing water services. Residents will have their individual service turned off for approximately 2 hours when the contractor works on the service. All homes are receiving a new 1.5” copper service from the water main to the right-of-way (property) line. The contractor will inform each home owner the day of the individual service shut-off.

When a home’s water service is shut off for any amount of time, some air will accumulate in the pipe. When the water gets turned back on, it is good for the resident to slowly turn a faucet back on for a few minutes, allowing the air to escape.

Friday, June 11, 2010

Water main work is progressing smoothly on Meadowlark and Terrace and should continue for the next week or two.

Friday, June 4, 2010

Construction has Begun

Water main installation began on Wednesday at the intersection of Meadowlark and Knollwood. 8” Ductile Iron Pipe is being installed along with new fire hydrants and new water services. Each house will receive a 1.5” copper service from the main to the B-Box. This work will continue for several weeks.

Friday, May 28, 2010

Thank you to those that attended our Resident Information Meeting this week! The contractor plans to begin work next Tuesday with material delivery, layout and tree removal/pruning. The first on the schedule is to begin water main on Meadowlark.