Tuesday, November 30, 2010

Work is substantially complete with the exception of punch list work.

Monday, November 22, 2010

The contractor is substantially completed with the work with the exception of remaining landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work.

Wednesday, November 10, 2010

The contractor is substantially complete with the work with the exception of manhole adjustments, pavement markings and remaining landscaping on Meadowlark and Terrace.

The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.

Friday, November 5, 2010

The contractor is substantially complete with the work with the exception of manhole adjustments, pavement markings and remaining landscaping on Meadowlark and Terrace.

The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.

Monday, November 1, 2010

The contractor is substantially complete with the work with the exception of landscaping on Meadowlark and Terrace.

The contractor has completed the hot-mix asphalt (surface) paving on Michael today (Monday, November 1).