Monday, November 22, 2010
Wednesday, November 10, 2010
The contractor is substantially complete with the work with the exception of manhole adjustments, pavement markings and remaining landscaping on Meadowlark and Terrace.
The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.
The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.
Friday, November 5, 2010
The contractor is substantially complete with the work with the exception of manhole adjustments, pavement markings and remaining landscaping on Meadowlark and Terrace.
The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.
The contractor has completed the hot-mix asphalt (surface) paving on Michael. The contractor is scheduled to complete the landscaping, manhole adjustments, re-installation of disturbed mailboxes, pavement markings and punch list work in the next couple weeks.
Monday, November 1, 2010
Friday, October 22, 2010
The contractor has paved the final lift of hot-mix asphalt (surface course) this week on Meadowlark and Terrace.
The contractor has completed work on curb and gutter, driveway and sidewalk replacement this week on Michael. The contractor is scheduled to grind the existing asphalt pavement late this week and prepare for hot-mix asphalt paving into next week on Michael.
The contractor has completed work on curb and gutter, driveway and sidewalk replacement this week on Michael. The contractor is scheduled to grind the existing asphalt pavement late this week and prepare for hot-mix asphalt paving into next week on Michael.
Friday, October 15, 2010
The contractor is scheduled to pave the final lift of hot-mix asphalt (surface course) next week on Meadowlark and Terrace.
Utility (water main) work has been completed on Michael Lane. The contractor is scheduled to work on curb and gutter, driveway and sidewalk replacement next week on Michael. Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter cures in front of their driveways. The contractor will notify residents that need to have their vehicles moved out of their driveways prior to concrete work.
Utility (water main) work has been completed on Michael Lane. The contractor is scheduled to work on curb and gutter, driveway and sidewalk replacement next week on Michael. Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter cures in front of their driveways. The contractor will notify residents that need to have their vehicles moved out of their driveways prior to concrete work.
Friday, October 8, 2010
The contractor will continue with utility structure adjustments on Meadowlark and Terrace into next week. The contractor is scheduled to pave the final lift (hot-mix asphalt surface course) on Meadowlark and Terrace in mid-October.
Utility (water main) work will be completed on Michael Lane this week. The contractor is scheduled to proceed with curb and gutter replacement and asphalt grinding later this month.
Utility (water main) work will be completed on Michael Lane this week. The contractor is scheduled to proceed with curb and gutter replacement and asphalt grinding later this month.
Friday, October 1, 2010
The contractor will continue with utility structure adjustments on Meadowlark and Terrace into next. The contractor is scheduled to pave the final lift (hot-mix asphalt surface course) on Meadowlark and Terrace in mid-October.
The contractor is scheduled to continue installing water services on Michael Lane into next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.
The contractor is scheduled to continue installing water services on Michael Lane into next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.
Friday, September 24, 2010
The contractor paved the first (of two) lift of asphalt on the northern section of Terrace this week. Next week the contractor is scheduled to complete utility structure adjustments on Meadowlark and Terrace.
The water main testing and chlorination has been completed and passed on Michael.
The contractor is scheduled to continue installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.
The water main testing and chlorination has been completed and passed on Michael.
The contractor is scheduled to continue installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.
Friday, September 17, 2010
All concrete work on Meadowlark and Terrace has been completed. The contractor is scheduled to start preparation of the aggregate base course on Terrace late this week, continuing into next week. The contractor is also scheduled to install the hot-mix asphalt binder course next week (weather permitting).
The water main on Michael has been installed and is being tested / chlorinated.
The contractor is scheduled to start installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.
The water main on Michael has been installed and is being tested / chlorinated.
The contractor is scheduled to start installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.
Friday, September 10, 2010
Thursday, September 2, 2010
Friday, August 27, 2010
All the underground work is complete on Terrace and Meadowlark! Replacement of curb and gutter is underway and should be completed sometime next week. Upon completion of curb and gutter installation next week, the contractor will begin grinding the surface of the roadway off for resurfacing.
Watermain installation has begun on Michael Lane and will continue for the next several weeks.
Watermain installation has begun on Michael Lane and will continue for the next several weeks.
Friday, August 20, 2010
The utility services are almost complete on Meadowlark and Terrace. Then there are just a few things left to do before curb & gutter work can begin, including removing existing fire hydrants. Curb and gutter removal and replacement should take place sometime next week.
On Michael Lane, the contractor is going to prepare the trench for water main installation. This is going to involve grinding the road surface exactly where the water main is going to be placed. This way, the rest of the road pavement will remain in place until the water main is installed. This grinding may take place today. The contractor plans to begin the water main installation early next week.
On Michael Lane, the contractor is going to prepare the trench for water main installation. This is going to involve grinding the road surface exactly where the water main is going to be placed. This way, the rest of the road pavement will remain in place until the water main is installed. This grinding may take place today. The contractor plans to begin the water main installation early next week.
Friday, August 13, 2010
Saturday, August 7, 2010
Meadowlark/Terrace
The contractor is done with utility services on Meadowlark and is continuing with the services on Terrace.