All the underground work is complete on Terrace and Meadowlark! Replacement of curb and gutter is underway and should be completed sometime next week. Upon completion of curb and gutter installation next week, the contractor will begin grinding the surface of the roadway off for resurfacing.
Watermain installation has begun on Michael Lane and will continue for the next several weeks.
Friday, August 27, 2010
Friday, August 20, 2010
The utility services are almost complete on Meadowlark and Terrace. Then there are just a few things left to do before curb & gutter work can begin, including removing existing fire hydrants. Curb and gutter removal and replacement should take place sometime next week.
On Michael Lane, the contractor is going to prepare the trench for water main installation. This is going to involve grinding the road surface exactly where the water main is going to be placed. This way, the rest of the road pavement will remain in place until the water main is installed. This grinding may take place today. The contractor plans to begin the water main installation early next week.
On Michael Lane, the contractor is going to prepare the trench for water main installation. This is going to involve grinding the road surface exactly where the water main is going to be placed. This way, the rest of the road pavement will remain in place until the water main is installed. This grinding may take place today. The contractor plans to begin the water main installation early next week.
Friday, August 13, 2010
Saturday, August 7, 2010
Meadowlark/Terrace
The contractor is done with utility services on Meadowlark and is continuing with the services on Terrace.
Subscribe to:
Posts (Atom)