The contractor paved the first (of two) lift of asphalt on the northern section of Terrace this week. Next week the contractor is scheduled to complete utility structure adjustments on Meadowlark and Terrace.
The water main testing and chlorination has been completed and passed on Michael.
The contractor is scheduled to continue installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.
Friday, September 24, 2010
Friday, September 17, 2010
All concrete work on Meadowlark and Terrace has been completed. The contractor is scheduled to start preparation of the aggregate base course on Terrace late this week, continuing into next week. The contractor is also scheduled to install the hot-mix asphalt binder course next week (weather permitting).
The water main on Michael has been installed and is being tested / chlorinated.
The contractor is scheduled to start installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.
The water main on Michael has been installed and is being tested / chlorinated.
The contractor is scheduled to start installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.
Friday, September 10, 2010
Subscribe to:
Posts (Atom)