Friday, September 24, 2010

The contractor paved the first (of two) lift of asphalt on the northern section of Terrace this week. Next week the contractor is scheduled to complete utility structure adjustments on Meadowlark and Terrace.

The water main testing and chlorination has been completed and passed on Michael.
The contractor is scheduled to continue installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.