Friday, September 17, 2010

All concrete work on Meadowlark and Terrace has been completed. The contractor is scheduled to start preparation of the aggregate base course on Terrace late this week, continuing into next week. The contractor is also scheduled to install the hot-mix asphalt binder course next week (weather permitting).

The water main on Michael has been installed and is being tested / chlorinated.
The contractor is scheduled to start installing water services on Michael Lane next week (weather permitting). Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.